The
cornerstone of the iSLP had always been the
provision of housing - the most essential
component of any integrated human settlement. The
basic requirement is land, and the available land
in the iSLP comprised 3 categories:
- "Greenfields" areas
- large tracts in which no development or
settlement had taken place;
- "Infill" areas -
undeveloped areas within existing townships
which had escaped development or settlement,
usually through policing. These areas
typically comprised "buffer strips"
between the racial ghettoes of apartheid
South Africa.
- Upgradeable Informal
Settlements - the number of informal
settlements in greater Cape Town had grown
rapidly through the 1980's and into the 90's,
and some were on land that would lend itself
to upgrading.
The intended strategy was to
synchronise the development of the greenfields
sites and the upgrading of the informal
settlements, so that most of the residents of
informal settlements could relocate to the
greenfields areas, releasing the informal
settlements for development. At the same time the
Infill areas would be developed, but primarily for
the benefit of the burgeoning population living in
shacks in the backyards of formal houses in the
old townships.
A complicating factor, however,
was that the greenfields areas were under the
ownership of the provincial government, whereas
the infill areas and informal settlements were
owned by local government. It was essential,
therefore, for the provincial and local government
housing departments to work in tandem. Whilst
there was agreement on this in principle, the
ability of the two different parties to deliver
has been very different - for reasons that relate
directly to the immense restructuring that has
taken place in government since late 1993 -
precisely when the implementation of the iSLP was
to commence.
One of the first products of the
dismantling of apartheid structures was the
abolition of the "Tricameral Parliament"
infrastructure, which resulted in a large number
of officials being redeployed in provincial
government departments. The Western Cape
provincial administration received a very
significant addition of experienced personnel, not
least within its Housing Department. As a result
the Province was more than capable of developing
its land within the iSLP.
Local government within the iSLP
project area had a completely contrary experience.
When the Implementation Phase began, all the
informal settlements within the iSLP were within
the ambit of small, under-resourced interim local
authority structures. When, in 1996, the local
authority structure in the whole metropole was
restructured, these potential projects came under
the ambit of one of the six metropolitan
sub-structures, which happened to be poorly endowed
with housing development expertise. As a result,
very little upgrading of informal settlements has
taken place. Some of the infill areas have become
informal settlements, and the balance have still
to be developed.
The consequence, therefore, has
been that the greenfields sites have been rapidly
developed, almost exclusively for the benefit of
residents of the informal settlements. Tragically,
however, as these households have relocated their
places in the informal settlements have been taken
by others, and the opportunity to reduce densities
in the informal settlements and to initiate
upgrading has been lost. This is the consequence
of the weakness of the local authority combined
with the economic and shelter pressures in a poor,
urbanising society.
For more details of the
residential development programme see Housing.
Running just behind the township
development process was the programme for
providing Education, particularly for
children. The provision of schools is an
indispensable component of any integrated human
settlement project. In South Africa the provision
of education is the responsibility of provincial
government, within policy parameters set by
national government.
The need for schools was
estimated on the basis of 1 primary school per
1 000 residential sites, and 1 secondary school per
2 000 sites. The budget was drawn up on this
basis, with 50% of finance to be made available by
the iSLP fund, and the balance provided from the
Education Department’s budget. However, as
implementation started, the Department was facing
a crisis within the iSLP project area - schools in
the existing townships were completely overcrowded
because of the impact of all the informal
settlements. There was an urgent need to extend
these schools at the same time as new schools
would be built in the greenfields areas. A massive
building programme was launched by the provincial
departments of Education and Works, through which
by mid-2000 11 schools had been extended and 16
new schools built: a total of 554 classrooms.
Almost all of the school
building to date has been financed from the iSLP
Fund. The balance must be financed from the
provincial budget, which currently is almost all
expended on operating costs. The Department has,
however, undertaken to meet its commitments to the
iSLP communities.
The Health needs of the
communities are addressed by the Health
Departments of the Province and of the local
authorities, in terms of a joint strategy. The
Province is responsible for the public hospitals,
including day hospitals and large community health
centres. The local authorities are responsible for
clinics and small community health centres, the
focus of which is children up to the age of 13.
Most of the iSLP Health budget
has been applied to the upgrading of 8 existing
facilities in the established townships -
increasing their capacity to address primary
health care needs. In the greenfields areas a
large community health centre and maternity &
obstetrics unit has been built in Delft, and a
smaller community health centre in Weltevreden
Valley. A 250-bed regional hospital is scheduled
to be built in Philippi East, and although it is
top priority for the health department the
required funding, both operational and capital,
will not be available to the Provincial Department
for a few years.
The other capital investment
component of the iSLP is the construction of
Civic Facilities - halls, sports fields and
libraries. These are the responsibility of the
local authority, and the iSLP provides the local
authority with 50% of the capital funding for
approved projects.
The many changes within local
authorities mentioned above have also made it
difficult to create new strategies for the
provision and operation of facilities. The current
"metropolitan sub-structures" are an
amalgam of previous structures which each had
their own policies and strategies. As a result the
new authorities inherited a very uneven
geographical distribution of facilities, to which
the operating budget is inescapably skewed. As a
result some of the capital investment decisions
within the iSLP have been made on a rather ad
hoc basis by the authorities, and not
everything that has been built has yet had access
to the necessary operational funds.
Notwithstanding this, 8 halls, 3
libraries and 4 sports fields have so far been
constructed, with another 2 halls and a swimming
pool (in Delft) being under construction.